1. Structure = 35%
2. Brick work = 6%
3. Wood work = 5%
4. Metal work = 2%
5. Plambing and Sanitary = 6%
6. Electrical work = 7%
7. Plaster work = 4%
8. General Floor Tiles work = 6%
9. Toilet & Kit wall Tiles work = 3%
10. Aluminium work = 4%
11. EME (Lift, Generator, Substation) = 10%
12. Paint work = 3%
13. Others civil work = 6%
14. Utility connection & Bill = 3%
Total = 100%

STRUCTURE 35%
– Footing & Column Padestal = 20%
– Grade Beam, UGWR top Slab = 5%
– GF Column, Stair etc = 4%
– 1st Floor Slab = 9%
– Typical Floor Column (5×3%) = 15%
– 2nd floor slab to roof slab (5×8) = 40%
– Roof top = 7%
TOTAL = 100% (৩৫% যেভাবে আসবে।)

BRICK WORK 6%
– GF Brick work = 6%
– 1st floor Brick work = 18%
– 2nd floor Brick work = 18%
– 3rd floor Brick work = 18%
– 4th floor Brick work = 18%
– 5th floor Brick work = 18%
-Roof Top Brick work = 4%
TOTAL = 100% (৬% যেভাবে হবে।)

WOOD WORK 5%
– Door frame = 40%
– Main Door Shutter = 15%
– Partex Door Shutter = 35%
– Cat Door & Accessories = 10%
TOTAL = 100% (৫% যেভাবে হবে।)

METAL WORK 2%
– Window grill = 55%
– Verandah Railling = 20%
– Stair Railling = 10%
– Main gate, Gen-Sub, safety grill = 15%
TOTAL = 100% (২% যেভাবে হবে।)

PLAMBING & SANITARY 6%
– uPVC vertical line thru duct = 25%
– GI line work = 30%
– Fixture & Fittings = 40%
– Ground Floor = 5%
TOTAL = 100% (৬% যেভাবে হবে।)

ELECTRICAL – 7%
– Conduiting inside slab = 10%
– Conduiting on wall i/c MK box=15%
– Cabling work = 55%
– Switch-Socket = 20%
TOTAL = 100% (৭% যেভাবে হবে।)

PLASTER 4%
– Ceiling plaster = 20%
– Internal wall plaster = 50%
– Outside plaster/facing bricks = 30%
TOTAL = 100% (৪% যেভাবে হবে।)

GENERAL FLOOR TILES 6%
– General floor & Verandah = 75%
– Stair, typical lobby & lift wall = 20%
– GF lift lobby, wall, reception = 5%
TOTAL = 100% (৬% যেভাবে হবে।)

TOILET & KIT WALL TILES = 3%
– Bath wall = 60%
– Kitchen wall = 20%
– Bath floor = 9%
– Bath counter top = 4%
– Kitchen floor = 3%
– Kitchen counter top =4%
TOTAL = 100% (৩% যেভাবে হবে।)

ALUMINIUM WORK 4%
– Outer framing-window sliding= 40%
– Glass shutter-window sliding = 30%
– Verandah sliding = 20%
– Toilet high window = 5%
– Comnon area = 5%
TOTAL = 100% (৪% যেভাবে হবে।)

EME 10%
– Lift = 50%
– Generator = 25%
– Substation = 20%
– PABX, Fire extinguisher etc = 5%
TOTAL = 100% (১০% যেভাবে হবে।)

PAINT WORK = 3%
– Upto putty = 40%
– Internal wall&ceiling 1st coat= 20%
– Internal wall&ceiling 2nd coat= 15%
– Outside paint/ceramic Tites = 25%
TOTAL = 100% (৩% যেভাবে হবে।)

OTHERS CIVIL WORK = 6%
– Boundary wall = 30%
– Line terracing/Roof top paver= 15%
– LOGO, Gardening & others = 4%
– GF BBC = 14%
– GF pavement & footpath dev = 10%
– Lintel, F/slab, drop wall, counter slab = 20%
– Cable tray = 1%
– Sanitary duct cover, ceiling etc= 4%
– Reception desk, letter box = 2%
TOTAL = 100% (৬% যেভাবে হবে।)

UTILITY CONNECTION & BILL = 3%
– DESA/DESCO = 35%
– TITAS = 20
– WASA = 15%
– Utility bills = 30%
TOTAL = 100%